Carlisle, Massachusetts · A new chapter for Ferns

We're working
to bring
Ferns back.

The vision is a welcoming country store and café—but first, Ferns needs a safe, lasting wastewater solution and the approvals to move forward.

See where things stand
The yellow Ferns Country Store building in Carlisle

A familiar corner,
planning its next chapter.

July 2026Environmental results are encouraging; wastewater feasibility is nextRead the wastewater update

Shaped by Carlisle

500+ neighbors shared what Ferns means to them.

The message was beautifully consistent: bring back the morning coffee, the quick lunch, the gallon of milk—and the feeling that you've arrived somewhere you belong.

That feedback is guiding every step: rooted in Ferns' history, built for everyday life, and designed to serve Carlisle for generations.

The new Ferns

One good stop. A hundred reasons to stay.

More market and café than convenience store—easy enough for every day, special enough to become a ritual.

From the kitchen

Food worth stopping for

Coffee, baked goods, breakfast, smoothies, açaí bowls, sandwiches, bowls, pizza, and easy family meals.

On the shelves

The basics, close to home

Milk, eggs, bread, butter, pantry staples—and, of course, the candy Carlisle remembers.

Grown nearby

Local by instinct

Fresh produce and thoughtful goods from area farms, bakers, makers, and artisans.

Around the table

Room to linger

Comfortable indoor seating, expanded patios, and a welcome for families, neighbors, and cyclists.

Design preview

Historic character, reimagined for everyday life.

Early concepts inspired by community feedback: a light-filled market and café, room to gather, and a renewed patio at the center of town. Scroll to explore.

Ordering & Bakery Counter
01Ordering & Bakery Counter
Market & Grocery
02Market & Grocery
Market & Refrigerated Goods
03Market & Refrigerated Goods
Take-Out Entrance
04Take-Out Entrance
Café & Restaurant Area
05Café & Restaurant Area
Wine Wall & Seating
06Wine Wall & Seating
Bar & Lounge Seating
07Bar & Lounge Seating
Renewed Patio
08Renewed Patio

July 2026 project update

A potential path is emerging.

Much of this year's progress has happened behind the scenes. Multiple rounds of environmental testing are complete, discussions with MassDEP have been encouraging, and the work has clarified the issue that will determine whether our proposed market and café can move forward: a safe, permanent wastewater solution.

*No wastewater connection or construction project has been approved. Capacity, routing, cost, permitting, and Town approval all remain to be determined through further study and public review.

Completed

Environmental testing

Soil, groundwater, and indoor air have been sampled through multiple rounds of testing to understand the property's historic petroleum impacts. The overall results have been very encouraging.

Additional monitoring wells are being installed to continue that work.

Conclusion reached

On-site options

Engineers spent months evaluating conventional septic, advanced treatment, neighboring land, and other alternatives. Four firms reached the same conclusion: the site's physical and regulatory constraints leave no approvable on-site solution.

A viable long-term wastewater plan is necessary to move forward with our proposed market and café.

Under consideration

The remaining path

The only remaining approach identified by our engineers is to study a connection to the existing wastewater treatment facility at the Carlisle School.

This is a possibility to evaluate—not an approved project.

Why study the school connection?

A promising option, with important questions still to answer.

The school facility has served the campus since 2006 and was originally designed with additional capacity. Weston & Sampson—the firm that designed and currently services the system—has been retained to evaluate whether a connection from Ferns is technically, environmentally, financially, and operationally feasible.

The study will also consider whether updated wastewater infrastructure could provide a broader benefit to Carlisle Center, including the Gleason Public Library. Carlisle explored a similar Town Center concept more than a decade ago; this study would revisit it using current conditions and updated engineering.

Read the 2010 background

What happens next

A study first. Decisions later.

  1. 01
    Authorize and complete the feasibility study

    Work collaboratively with the Town to determine whether the proposed connection can be studied and whether it is viable.

  2. 02
    Review the findings publicly

    If the study is encouraging, the concept would still require Town discussion, confirmation of capacity, and an agreement allowing Ferns to use the facility.

  3. 03
    Move into design and permitting

    Detailed engineering, funding discussions, public review, permitting, and MassDEP approval would all follow before construction could proceed.

Read the complete wastewater update
The porch and flags outside Ferns Country Store

The corner that remembers

A store has lived here for more than a century.

This corner has been a superette, gas station, post office, general store, and gathering place.

In its Ferns years, it became part of Carlisle's daily rhythm: kids choosing candy after school, cyclists refueling, neighbors catching up over coffee. The store closed in May 2025, ending one era and beginning the work of the next.

“Not just a stop for essentials—a place where everyday life happened.”

Full project context · July 2026

Understanding the Wastewater Challenge

01Why hasn't Ferns reopened?

We've spent the past year working with engineers, environmental consultants, MassDEP, and Town officials to understand what would be required to safely reopen Ferns under our proposal. As part of our effort to purchase the property, which remains subject to an environmental lien held by MassDEP, the site has undergone a more comprehensive engineering and regulatory review than prior operations required.

That review confirmed that the existing wastewater system is substantially undersized for commercial use. The previous operation also functioned under significant wastewater restrictions, including composting toilets and operational limitations intended to reduce wastewater generation.

Throughout this process, MassDEP has emphasized that our proposal requires a long-term wastewater solution. Wastewater is the largest challenge, but it is not the only one: the property also requires continued environmental remediation, including groundwater cleanup as part of its long-term restoration. We have continued investing in this work because we believe the property can be responsibly restored for future generations.

Four different engineering firms have evaluated the property, considering conventional septic systems, neighboring land, advanced wastewater treatment technologies, composting toilets, tight tanks, and other potential approaches. Despite exploring every viable option, none of the four engineering teams identified an on-site wastewater solution they believed could be approved for our project.

02Why can't Ferns simply reopen with a new septic system?

We wish it were that simple. Those who read our previous update may remember that we were exploring a potential wastewater solution at Center Park. While we were hopeful, additional engineering and environmental review ultimately determined that it was not a viable solution.

Ferns sits on a very small parcel within a Zone I Wellhead Protection Area, surrounded by similarly constrained properties. Because of the site's location, every option had to protect the public drinking water supply while meeting stringent environmental requirements.

Without a sewer connection, wastewater in the Town Center is treated by individual septic systems and released through the soil back into the same groundwater system that supplies nearby drinking-water wells. That connection is why septic use is so tightly constrained here. Under Title 5, Zone II wellhead protection areas are considered nitrogen-sensitive, and new construction is generally limited to 440 gallons of design flow per day per acre. MassDEP's Zone I policy also states that Title 5 systems should be removed from Zone I areas whenever possible.

A market and café of Ferns' size requires approximately 2,145 gallons of wastewater capacity per day, while the existing system is approved for only 970 gallons per day. Engineers also determined that a compliant disposal field would require more land than is available on the property and surrounding parcels while still meeting the required setbacks from nearby drinking-water wells and other protected resources.

Unfortunately, this isn't simply a matter of installing a larger septic system. The combination of wastewater volume, limited available land, and drinking water protection requirements made it impossible for any of the four engineering teams to identify an approvable on-site wastewater solution.

03Did you look at alternative wastewater technologies?

Yes. Four engineering firms evaluated conventional and advanced treatment options, composting toilets, tight tanks, restroom trailers, relocating the water supply and the use of neighboring land. The problem is not limited to toilet waste. A market and café also generate commercial wastewater through food preparation, dishwashing, cleaning and other kitchen operations.

None of the on-site alternatives provided a permanent solution that could satisfy the site’s physical and regulatory constraints.

04Why not use a tight (holding) tank?

Based on the wastewater volume generated by a commercial operation, a tight tank would require extremely frequent pumping and ongoing maintenance, making it an impractical long-term solution.

05Why are you studying a connection to the Carlisle School?

After months of evaluating on-site wastewater options, our engineers concluded that a connection to the Carlisle School wastewater treatment facility may be the only viable path for our proposed project. During discussions with MassDEP, the school connection emerged as the most viable remaining long-term approach to evaluate. Whether it is feasible, and whether it could receive the necessary approvals, remains to be determined.

We recognize this may sound like an extraordinary solution for a small country store that has served the community for more than a century. We felt the same way when the idea was first raised. We definitely didn't set out to pursue a sewer connection. That's why we spent months exploring every realistic on-site option first. Four different engineering teams independently evaluated expanding the existing system, neighboring land, advanced wastewater treatment technologies, and other potential approaches before ultimately reaching the same conclusion.

The school's treatment facility is located approximately 1,200 feet from Ferns and has existed for decades. In fact, a 2010 Town study identified extending wastewater infrastructure into Carlisle Center as a potential long-term solution for the area's wastewater challenges.

To determine whether this is a realistic option, Weston & Sampson has been retained to conduct a comprehensive feasibility study. The study will evaluate whether the school has sufficient available treatment capacity, whether a connection is technically, environmentally, financially, and operationally feasible, what infrastructure would be required, and what Town and MassDEP approvals would be necessary.

If the study concludes that a connection is possible, there would still be significant engineering, permitting, regulatory review, funding discussions, and Town approvals before any project could move forward.

If feasible, conveying commercial wastewater from one of the most environmentally constrained properties in Carlisle to an existing wastewater treatment facility would represent a fundamentally different approach to protecting Carlisle's public drinking water supply while allowing Ferns to reopen responsibly.

06Does this mean a sewer is definitely happening?

Not yet. The feasibility study will determine whether the connection is technically and operationally possible. Any connection would require Town approval, an agreement allowing Ferns to use the facility, confirmation of available treatment capacity, and approval from MassDEP. The school facility’s permit may also need to be modified to recognize Ferns as an additional wastewater source.

07Has MassDEP prevented Ferns from reopening?

No. Our experience with MassDEP has been overwhelmingly positive. They have spent countless hours working with us, our engineers, and our environmental consultants to understand the site's challenges and evaluate every reasonable path forward. Throughout this process, they have been collaborative and genuinely interested in helping identify a safe, long-term solution that protects Carlisle's public drinking water supply while returning the property to productive use.

The wastewater limitations at Ferns are long-standing and predate our involvement with the property. MassDEP has consistently worked with our engineers and environmental consultants as different concepts have been explored. Their role has been to help evaluate whether interim and permanent approaches could meet applicable public-health and environmental requirements. That review has clarified that the existing wastewater system is substantially undersized and that any interim approach would need to be tied to a firm, enforceable commitment to a permanent wastewater solution.

08Could wastewater infrastructure benefit more than just Ferns?

Potentially, yes. Although our immediate goal is simply reopening Ferns, the engineering work has highlighted broader infrastructure challenges within Carlisle Center. If future studies determine additional wastewater infrastructure is feasible, it could provide long-term benefits beyond a single property.

09If the challenges are so significant, why are you still pursuing Ferns?

Because we believe the community deserves to have Ferns reopened. If this were a financial decision, we wouldn't still be here.

Over the past year, we've invested significant time and resources into engineering, environmental investigation, and planning because we believe Ferns is an important part of Carlisle. We feel a responsibility to explore every realistic path before giving up.

What has kept us moving forward is that the environmental investigation has been encouraging. Groundwater petroleum concentrations have generally declined over time, indoor-air testing found no solvents or degreasers, and the detected compounds were well below applicable health-based thresholds. While additional work remains, those results gave us confidence that the property's environmental challenges can be responsibly addressed.

We don't know whether Ferns will ultimately reopen, but as long as there is one potential path forward, we believe it's worth continuing to explore every opportunity to make it happen.

10When will Ferns reopen?

The next step is determining whether the Town will authorize a feasibility study of the school connection. If the study confirms sufficient capacity and technical feasibility, the project would then move through detailed engineering, agreements with the Town, permitting, and MassDEP review.

Our hope is that restoration of the building could begin once there is a clear, approved path for permanent wastewater, rather than waiting until every portion of the wastewater infrastructure has been constructed. MassDEP indicated they would be willing to evaluate interim wastewater approaches if there is a firm, enforceable commitment to a permanent wastewater solution. Any interim approach would still require additional review and approvals from the Town, but it could provide a path for Ferns to reopen while the permanent infrastructure is being completed.

11When can we start talking about sandwiches and coffee instead of...well...poop?

Hopefully soon. We know the community is eager to get back to talking about coffee, sandwiches, and seeing neighbors again. We are too.

The next step is seeking Town approval to move forward with the feasibility study to determine whether a connection to the Carlisle School wastewater treatment facility is technically, environmentally, operationally, and financially feasible.

Our hope is that the permanent wastewater infrastructure does not need to be fully constructed before restoring Ferns. Rather, we need confidence that there is a clear and durable path forward before investing millions of dollars into the building itself.

Once that path is established, we hope restoration of Ferns can move forward while the permanent wastewater solution continues through construction.

12How can I help?

Community support truly makes a difference.

If you want to see Ferns return, please consider submitting a letter of support. A strong showing from the community will help demonstrate to Town officials how important Ferns is to the community and the vitality of Carlisle Center.

As important decisions are made in the months ahead, we hope the community’s support, and the value of restoring Ferns as a local gathering place, market, and community asset, will be given serious consideration.

Thank you for your support and encouragement throughout this process. Please feel free to reach out with any additional questions.

The future of Ferns

Come along for
the next chapter.

Get progress notes, milestones, and the first word on what's happening at Ferns.